March 7, 2022Buttes Emergency Well Replacement Project
UPDATE 3/21/2023
Unfortunately, supply chain delay issues continue to stall this project. The contratcor is waiting for the final piece of equipment that is anticipated to be recieved in 6 - 7 weeks. The contractor will then have 20 days to complete phase 2 of this project. At this point we anticipate completion by the end of May 2023.
UPDATE 11/4/2022
Contractor is scheduled to be onsite beginning next week November 10th to begin Phase 2 scope of work. As stated below this scope of work will include installation of new watermain, control panels, generator and full integration with the existing system. This scope of work is projected to be complete in March 2023.
Please contact the District if you have any questions or concerns regarding this project.
UPDATE 9/19/2022 - DELAYED
The initial work of Phase 2 (connecting the new well to the existing system) is anticipated to take place in early to middle of October. The next phase of work will include installation of new watermain from the new well to the existing watermain infrastructure. The new well will not be integrated or operational until the control panels and new generator are installed and programmed in March/April of 2023. This scope of work should NOT have any impact to the existing system operations or access to the community. The delay in project completion is due to supply chain issues in obtaining the electrical controls and generator.
Please contact the District if you have any questions or concerns regarding this project.
UPDATE 07/19/2022
The development and drilling of the well has been completed. Beginning Wednesday July 20th the well driller will be performing a 24 hour flow test on the well. This will not result in any water restrictions but residents may notice noise from the engine being used for the pumping and flow of water from the well site.
Phase 2 of connecting the new well to the distribution system will begin with the pipe installation in late July or early August. Unfortunately the installation of the controls and generator will not take place until closer to March 2023 due to supply chain issues.
Please contact the District if you have any questions or concerns regarding this project.
Thank you - Valley Water District 253-841-9698
Buttes Emergency Well Replacement Project is scheduled to begin the week of March 21, 2022 - click the link below for more information.
Buttes Emergency Well Replacement Project Letter